Labour total, rate and efficiency variance 2 / 5

The total labour variance can be subdivided between labour rate variance and labour efficiency variance.

Total labour variance
direct labour total variance =actual units should have cost$x
actual units did cost$x
-------
direct labour total variance$x (f/a)
=====
direct labour rate variance =actual hrs should have cost$x
actual hrs did cost$x
-------
direct labour rate variance$x (f/a)
=====
direct labour efficiency variance =actual units should have takenx hrs
actual units did takex hrs
---------
efficiency variance in hrsx hrs (f/a)
x standard rate per hr$x
---------
efficiency variance in $$x (f/a)
======

The direct labour total variance is the difference between what the output should have cost and what it did cost, in terms of labour.

The direct labour rate variance is the difference between the standard cost and the actual cost for the actual number of hours paid for.

In other words, it is the difference between what the labour did cost and what it should have cost.

The direct labour efficiency variance is the difference between the hours that should have been worked for the number of units actually produced, and the actual number of hours worked, valued at the standard rate per hour.

In other words, it is the difference between how many hours should have been worked and how many hours were worked, valued at the standard rate per hour.

variancefavourableadverse
labour rate

use of apprentices or other workers
at a rate of pay lower than standard
wage rate increase
use of higher grade labour
idle time


the idle time variance is always
adverse

machine breakdown
non-availability of material
illness or injury to worker
labour efficiency





output produced more quickly than
expected because of work motivation
better quality of equipment or
materials, or better methods.
errors in allocating time to jobs
Using more experienced labour


lost time in excess of standard
allowed.
output lower than standard set
because of deliberate restrictions,
lack of training or sub-standard
material used.
errors in allocating time to jobs

Illustration - Labour rate variance

Standard cost/hour $5
Actual hours 45,400
Actual amount paid for actual hours $224,515

What is the labour rate variance?

Solution

45,400 should pay 45,400 x $5= $227,000
Did pay $224,515

Labour rate variance is $2,485 Favourable (Paid less than should have)

Illustration - Labour efficiency variance

Actual production 8,900 units
Standard hours/unit 5 hours at $5/hour
Actual hours worked 44,100

What is the labour efficiency variance?

Solution

Should work 8,900 x 5 hours = 44,500 hours
Did work 44,100

Labour efficiency variance is 400 hours x $5/hour = $2,000 Favourable (We paid less than we should have)

Illustration - Idle time variance

Actual hours paid for 45,400
Actual hours worked 44,100
Standard rate/hour $5

What is the idle time variance?

Solution

(Actual hours paid-Actual hours worked) x standard rate per hour
= (45,400 - 44,100) x 5
= $6,500 Adverse (Idle time is always a bad thing!)

We use cookies to help make our website better. We'll assume you're OK with this if you continue. You can change your Cookie Settings any time.

Cookie SettingsAccept